SZ/OEMU/29/1/16 - Notes on the siting and construction of air raid shelter tunnels, 24/10/41
SZ/OEMU/29/1/16
Item
Notes on the siting and construction of air raid shelter tunnels, 24/10/41
1941
8 leaves
R.C. 262
Lists the conditions air raid shelter tunnels should meet and the optimum conditions for the construction of a satisfactory tunnel. Discusses protection against bombs, hygiene, cost, geological matters, roof design, and drainage.
Corrigenda slip attached.
Lists the conditions air raid shelter tunnels should meet and the optimum conditions for the construction of a satisfactory tunnel. Discusses protection against bombs, hygiene, cost, geological matters, roof design, and drainage.
Corrigenda slip attached.
-
SZ - Zuckerman Archive
-
SZ/OEMU - Ministry of Home Security, Oxford Extra-Mural Unit
-
SZ/OEMU/29 - [OEMU. CDRC - Shelters, beams, and walls]
-
SZ/OEMU/29/1 - [OEMU. CDRC - Shelters, beams, and walls. File One]
- SZ/OEMU/29/1/16 - Notes on the siting and construction of air raid shelter tunnels, 24/10/41
-
SZ/OEMU/29/1 - [OEMU. CDRC - Shelters, beams, and walls. File One]
-
SZ/OEMU/29 - [OEMU. CDRC - Shelters, beams, and walls]
-
SZ/OEMU - Ministry of Home Security, Oxford Extra-Mural Unit